From time to time there are issues with completing the function "Make Unit Ready". As well when a Unit goes on Notice to Vacate, you may need to update the Unit Status from "Ready" to "Not Ready".
The steps listed below will allow you to change the unit status for a specific unit.
You'll go to the specific Unit.
Click on "Change Unit Status" under Actions on the left-hand screen.
Complete the following fields:
- Type: Select "Unit Status"
- Unit Status: Select "Not Ready"
- Description: enter Not Ready (or NR)
Click on the "OK" button
Once that is completed, the Status is updated on the Unit and the Availability Report.